Yangjiang unit 3 connected to grid
time2015-11-25  fromHXCC  Viewed2337 times

   

    Unit 3 of Yangjing NPP that built by HXCC was connected to grid at 15:00 on 18 October. During the process of grid connection, Unit 3 was in a good condition with each of its working parameter kept normal and stable. The reactor formally enters into the commercial operation preparation phase which laid a solid foundation for power generation and full capacity operation of the following units.

    Main work of Yangjiang unit 3 reactor building was started on 15th of November in 2010. On 9th of June in 2012, the dome was placed six days ahead of Level Three schedule, which demonstrates construction of Chinese CPR1000 unit firstly realized the objective of finishing civil works of the nuclear island within nineteen months after FCD.