FCD of Yangjiang Nuclear Power Plant Unit 5
time2013-10-23  fromHXCC  Viewed3211 times

    On 18th September, first concrete pouring for raft foundation of unit 5 was started along with the announcement of Mr. Hao Zhijian, Managing Director of Yangjiang Project of China Nuclear Power Engineering Co., Ltd. (CNPEC) and drew the curtain for its nuclear island construction . The ceremony was participated by National Nuclear Safety Administration(NNSA), China General Nuclear Yangjiang Nuclear Power Co., Ltd., CNPEC Yangjiang Nuclear Power Engineering Co., Ltd.

    On 24th of January 2013, HXCC Yangjiang Project Management (HXCC-YPM) was requested to meet the goal of realizing FCD of unit 5 on 15th of August while keeping the work of unit1-4 on progress. In face of the heavy work load, HXCC-YPM bravely undertook the work and made meticulous preparation, by which the foundation pit was accepted by NNSA and handed over on 28th of February. Subsequently, the bed cushion was poured on 4th of March, inside&outside of the gallery was backfilled and rebar fixing was started on 9th of May. By 25th of June, the raft foundation was ready for the concrete pouring. On 13th of September, CNPEC send the work order and all the concrete was poured in four days. According to work plan, 4452 m3 were poured for the raft foundation by the application of mass concrete pouring technique in 45 hours.

closed
 
Copyright © 2011 www.
All Rights Reserved CHINA NUCLEAR INDUSTRY HUA XING CONSTRUCTION COMPANY LIMITED
[ICP05006750]
:    118棋牌网站   火萤棋牌手机客户端   FG梭哈   3000万彩票网站   星罗棋牌平台